The final Investment Grade Proposal was actually submitted in advance of the original deadline and works then programmed to commence in October which ended up being perfectly timed to coincide with the second lockdown!

Once again this was a perfectly reasonable opportunity for the Asset+ team to request an extension to the set programme but with the adapted Covid working procedures established through the IGP period the team were confident of being able to continue meeting the timescales they had agreed with Dudley.

Despite a third lockdown coming into play from January, the works have continued to meet the original programme with an application through the Public Sector Decarbonisation scheme submitted for Phase 2 works along the way.

Overall the scheme is providing the following annual savings for Dudley;

  • 10,442,653kWh
  • 2,022tCO2e
  • £431,371